Search

    Select Website Language

    AMACO Energy Group, a Greek multinational, is proposing an answer to one of the hardest questions facing Africa’s artificial intelligence (AI) ambitions today: where will all the electricity needed to run the servers come from?

    The company’s HERCULES project combines electricity generation, cooling and AI data-centre infrastructure. The idea is to reduce dependence on the national grid by generating electricity close to where it is consumed. The initial design uses liquefied natural gas (LNG), although AMACO says the system can later accommodate renewable energy and hydrogen.

    Theodore Theodoropoulos, AMACO’s founder and chief executive, is in Nairobi to discuss the proposal with Kenyan officials and potential partners, according to an email sent to TechCabal.

    “HERCULES has the potential to transform Mombasa Port and Kenya into a global AI Data Center hub by integrating advanced, independent smart-power generation directly with AI-DC infrastructure,” AMACO said in the email. 

    “Designed as a next-generation solution, it offers a highly mobile, scalable, adaptive and energy-efficient platform that can be deployed independently of the conventional electricity grid.”

    There is plenty to prove. The project has not been built, and questions remain over financing, customers, approvals, fuel supply, and the environmental case for using LNG. Africa has no shortage of ambitious infrastructure proposals that failed to progress beyond announcements.

    But the thinking behind HERCULES is more interesting than the question of whether one $1.5 billion project succeeds. AI is bringing data centres and electricity systems closer together. Global data-centre electricity consumption was about 415 terawatt-hours in 2024 and could reach 945TWh by 2030, with AI being the main driver of that increase.

    What might Africa learn from AMACO’s approach? Five lessons stand out.

    Build the power with the data centre

    The most useful idea in HERCULES is that if you want to build a very large AI data centre on the continent, work out where its electricity will come from at the same time.

    This has not always been necessary. A conventional data centre might require 10MW-25MW. An AI-focused hyperscale facility can require 100MW or more — enough electricity to supply about 100,000 households. The largest facilities being planned globally are measured in gigawatts.

    That makes the power supply part of the design decision.

    AMACO is testing that logic with its proposed Mombasa data centre. HERCULES puts generation alongside the data centre and integrates the two systems directly. The company says this avoids reliance on national grids and allows capacity to be expanded as computing demand increases.

    The rest of the continent could learn from this.

    A government trying to attract 500MW of new data-center capacity should have an answer for where the electricity will come from. Otherwise, the success of one infrastructure policy can create a problem for another.

    The timelines also matter. The International Energy Agency (IEA) notes that a data centre can be operational within two or three years, while the electricity infrastructure needed to support one can take considerably longer to plan and build. It estimates that grid constraints could delay about 20% of planned data-centre projects globally unless they are addressed.

    So plan them together.

    Do not assume the grid can absorb everything

    AMACO’s decision to make HERCULES capable of operating independently of national grids is particularly relevant to Africa.

    Kenya’s electricity demand reached a record peak of 2,439MW in December 2025, up 151MW from a year earlier. Thermal generation rose 24% in the first half of the 2025/26 financial year as electricity demand increased, while imports from Ethiopia and Uganda rose almost 25%.

    Now put a 100MW AI data centre into those numbers. One facility would have a potential demand equivalent to about 4% of Kenya’s current national peak.

    That does not mean Kenya lacks the electricity to host data centres. Its geothermal resources and high share of renewable generation are considerable advantages.

    But it does suggest that African countries should be wary of treating hyperscale facilities like ordinary commercial facilities.

    AMACO’s answer is dedicated generation. Other developers may choose different arrangements. Governments could require large data-centre projects to finance additional generation or transmission infrastructure. Dedicated renewable plants and storage are another possibility.

    If AI infrastructure brings enormous new electricity demand, it should ideally bring new electricity supply with it.

    Ask about the cooling system early

    HERCULES does something else differently. It treats cooling as part of the power system.

    This is becoming more important as AI chips increase the amount of computing that can be packed into a server rack. Higher density means more electricity and more heat.

    AMACO proposes recovering heat and cold within the same system used to generate electricity. The company also says its Mombasa project would avoid putting additional pressure on local water resources.

    That is a consequential claim in Mombasa.

    The coastal city has long struggled with water shortages and relies heavily on supplies from outside the county. A large industrial user cannot assume water is simply available because it needs it.

    Data centres use very different amounts of water depending on their cooling technology, location and design. Some newer facilities use closed-loop liquid cooling systems that substantially reduce direct water consumption. Others can consume large quantities.

    This should be established before a project is approved.

    How many litres of water will a facility consume for each kilowatt-hour of computing? Where will the water come from? What happens during shortages? Does the cooling technology require potable water? Can waste heat be put to another use?

    These questions are easier to answer before construction than after residents and data centres find themselves drawing from the same constrained supply.

    Mombasa is part of the idea

    The location AMACO has chosen also deserves attention. Most of Kenya’s existing data-centre capacity is concentrated around Nairobi. That makes commercial sense. The capital contains the banks, telecom companies, technology businesses and government agencies that buy much of the capacity.

    Mombasa has a different proposition. Several submarine cables connecting Kenya to international internet networks land at the coast. It has a major port, which suits AMACO’s LNG plans. A large data centre there would therefore sit close to both its proposed fuel supply and international connectivity.

    There is a lesson here that has little to do with LNG. African governments tend to talk about technology clusters in terms of cities that already have technology companies. Large AI infrastructure makes energy geography more important.

    A country could instead ask where electricity and fibre are cheapest and most plentiful, then consider whether computing capacity should follow them.

    Kenya’s geothermal resources provide one possibility. Ethiopia’s hydroelectric resources provide another. Nigeria and Mozambique have gas. Morocco has invested heavily in solar and wind.

    The location of Africa’s next large data-centre clusters does not have to follow the map of its startup ecosystems.

    Do not assume LNG is the lesson

    HERCULES has a complication. Its initial answer to AI’s rapidly growing electricity consumption is another fossil fuel.

    There is a commercial logic to LNG. Gas generation is dispatchable, and data centres need electricity continuously. The IEA estimates that natural gas currently supplies about 26% of data-centre electricity globally and expects gas generation serving data centres to continue growing.

    But AMACO is proposing this in Kenya, where the electricity mix makes the case less straightforward.

    The country has about 1GW of geothermal capacity. Geothermal has one of the qualities that makes gas attractive to data-centre operators: it can produce electricity continuously. Kenya also gets most of its electricity from renewable sources.

    An LNG-based system, therefore, needs to demonstrate an advantage over the alternatives on cost and reliability sufficient to justify imported fuel and higher emissions. There is also the customer side.

    Large technology companies are trying to reduce the carbon footprint of their data centres at the same time as AI is increasing their electricity consumption. The carbon intensity of a data centre could therefore affect its attractiveness to the companies AMACO hopes will use it.

    AMACO says HERCULES can incorporate renewable energy and eventually hydrogen. That may turn out to be more important than the LNG component itself. The architecture can travel without fuel.

    Kenya could pair large computing facilities with geothermal. Ethiopia could explore hydro. Countries with abundant gas may decide that gas makes sense. 

    Solar-rich markets may require a mixture of solar, storage and firm generation. AMACO’s contribution is to put the energy choice at the centre of the data-centre decision.

    Finally 

    None of these answers whether AMACO will build HERCULES in Mombasa. That depends on details that have not yet been made public. The $1.5 billion financing is one. The size of the proposed data centre is another. 

    Customers, electricity costs, LNG requirements, water consumption and the amount of additional generation available to Kenya will all determine whether the project makes commercial sense.

    Those details should receive more attention than the headline investment figure. But AMACO is raising these questions at a useful time.

    True scale demands moving beyond surface-level integrations to robust execution. We’ve filtered the noise out of Moonshot 2026, optimising the conference strictly for high-calibre connections between startup founders, global financial operators, enterprise leaders, and individuals rewiring Africa’s technical frameworks. Get 20% off Early Bird tickets for a limited time.

    Previous Article
    African content has found a global market. Now comes the fight over the money
    Next Article
    Galaxy Watch 9 vs Galaxy Watch Ultra 2: Full comparison

    Related Diaspora Updates:

    Are you sure? You want to delete this comment..! Remove Cancel

    Comments (0)

      Leave a comment